The Stakes
Why GRW Was Engaged
Operating Conditions
Logistics & Access
Equipment Reliability
Coordinated access, material placement and installation sequencing with Ledcor’s team and the project engineers, accounting for the steep terrain and shared transportation corridor.
Used rope access to reach steep work areas and removed existing mesh as part of the rockfall mitigation scope.
Installed 40 rock bolts and support posts up to seven metres high to support the engineered attenuator systems.
Installed three Geobrugg attenuator sections totalling approximately 233 metres, with mesh drapes extending up to 60 metres downslope to guide falling rock toward designated collection areas.
If you are facing a complex project such as high-wall failure difficult-access slope issue, or something similar to this project, contact GRW’s Technical Response Team today!